July 29, 2022 – The paint striping was completed and the lot was opened up for traffic.
July 21, 2022 – The final lift of bituminous is scheduled for Friday, July 22nd. The only work remaining will be the paint striping which is expected to take place next week.
July 15, 2022 – The first of two lifts of bituminous was installed this week. The second lift is scheduled for early next week followed shortly by the paint striping. The parking lot will be reopened shortly thereafter.
July 8, 2022 – The concrete curb & gutter was installed this week. Finish grading and paving is expected to take place next week
June 30, 2022 – The old pavement has been removed and the contractor is currently grading and installing the aggregate base. The concrete curb & gutter and driveway will be installed early next week with final shaping of the aggregate base and paving to follow shortly thereafter.
June 24, 2022 – The contractor, Jensen Excavating, plans to begin work next week with removal of the existing pavement.