2024 Neighborhood Improvement Project Updates – Job 2401

September 13, 2024 

Spicer Road Reconstruction & Watermain: Ulland Brothers placed the final lift of new asphalt this week. All work is not complete except for minor punch list items.

Hammer Road east end reconstruction: This week the contractor placed both lifts of new bituminous surface. All work is now complete except for minor punch list items.

September 6, 2024

The sod was placed on all areas disturbed by the project this week. All work is now complete except for minor cleanup and punch list items.

Spicer Road Reconstruction & Watermain: The sod was placed on all areas disturbed by the project this week. Next week the contractor plans to install the final lift of asphalt on the street.

Hammer Road East End Resurfacing: Work began this week with removal of the existing asphalt surface on the dead end segment at the east end of Hammer Road. They are currently working on reshaping and regrading the existing aggregate base and plan to begin installing the new bituminous surface next week.

August 30, 2024 – The only work that took place this week was some prepping of the disturbed areas for sod and some minor cleanup. The sodding subcontractor plans to begin installing the sod next week.

August 23, 2024 – The only work that took place this week was some minor cleanup. The landscaping subcontractor anticipates starting sod placement next week.

August 16, 2024 – The edge milling was performed on Monday. Placement of the bituminous overlay started yesterday and will be completed by early next week. The only work remaining after that will be placement of sod on all disturbed areas.

Spicer Road Reconstruction & Watermain: The first of two lifts of asphalt was placed this week. They do not have a definite schedule for placing the final lift yet, however residents to have full access to their driveways. The sod work will likely take place next week in conjunction with the rest of the neighborhood area.

August 9, 2024 – All the concrete work will be completed by the end of today. Next week will be another busy week on this project. The contractor plans to perform the edge milling on Monday. There will be a few days of patching and cleanup work, and then the bituminous overlay is scheduled to be placed Thursday and Friday next week.

Spicer Road Reconstruction: The concrete work was completed this week. The first lift of asphalt will be placed next week in conjunction with the overlay in the neighborhood area.

July 26, 2024 – No work took place this week. The contractor plans to finish removals for the curb replacement throughout the project area. Any affected driveways will have gravel put in for temporary access. The concrete subcontractor is scheduled to begin installing new curb the week of August 5th.

Spicer Road Reconstruction – No work took place this week. The new aggregate roadbase has been installed so that residents can have access to their driveways. The concrete subcontractor plans to begin installing the new curb at the same time they are doing the concrete work in the neighborhood area (week of August 5th).

July 19, 2024 – The contractor removed most of the curb & gutter scheduled for replacement this week. They are leaving affected driveways in place because the concrete subcontractor currently doesn’t have an opening for another two weeks until they are able to begin installing the new curb.

Spicer Rd Watermain & Reconstruction – Ulland Brothers completed the replacement of water services up to the curb stops yesterday. The watermain replacement portion is now complete. They have now started on excavating and installing the new aggregate roadbase. The plan will be to perform the curb & gutter installation at the same time the concrete subcontractor is in town to complete work in the mill & overlay areas.

July 12, 2024 – This week the contractor completed repairs to manholes and catch basins. The next phase of this project is replacement of miscellaneous settled or damaged curb. They are trying to time this with when the new curb is getting installed on the Spicer Rd project.

Spicer Rd Watermain & Reconstruction: A lot is happening this week. The contractor has completed removal of the pavement and curb, and they have set up the temporary water supply. Today they started replacing the watermain and hope to finish either tomorrow or early next week. Once the new main is installed they will perform the required pressure and bacteria tests and then begin replacing the services up to the curb stops.

July 10, 2024 – The contractor is currently working on the repairs and adjustments to the manholes and storm inlets in the project area. This work will continue next week.

Spicer Road Watermain & Reconstruction: This week the contractor set up the temporary water supply and will begin removing the existing pavement and curb. Watermain replacement will begin later this week or early next week.

June 28, 2024 – The contractor plans to begin work either late next week or the following week. The first steps will be removing and replacing damaged or settled sections of curb & gutter in the mill & overlay areas. They will also begin making repairs to manholes and storm sewer inlets in the project area.

June 21, 2024 – Ulland Brothers has not been able to set a start date for this project yet due to weather delays on other projects. They are hoping to be able to start the miscellaneous curb replacements within the next couple of weeks.

June 5, 2024 – A preconstruction meeting to discuss this project will take place this week. The contractor, Ulland Brothers, has indicated they intend to start the miscellaneous curb & gutter work in the mill & overlay areas next week (week of June 10th).