September 24, 2021: This week the contractor finished paint striping the lot. The only remaining items are some small punch list items.

September 17, 2021: This week the contractor, Ulland Brothers, placed the final lift of asphalt on Monday, 9/13/21. The only remaining work is paint striping which is tentatively scheduled for late next week and misc. punch list items.