Plaza Street Culvert Repairs Updates – Job 1913

October 1, 2021: This week the street was paved and site restoration took place. The only work remaining is minor punch list items.

September 24, 2021: Work this week included backfilling around the new culverts, installing riprap at the culvert ends, and installing the new aggregate roadbase. Bituminous paving and site restoration are tentatively scheduled for next week.

September 17, 2021: This week the contractor placed the new box culverts and began the backfilling process. Next week they will begin rebuilding the road over the culverts.

September 10, 2021: This week the contractor removed the existing metal culverts and began excavating and installing the aggregate base for the new concrete pipes. They will begin installing the new culvert next week.

September 3, 2021: This week the contractor excavated the temporary stream diversion to route Bancroft Creek around the culvert area.They will also begin removing the existing culverts. Next week they will begin excavating for and installing the new box culverts.

The contractor will begin removing the pavement and digging the temporary channel adjacent to the existing culverts the week of August 30, 2021. Work is expected to take approximately 3 weeks.